Minesto's tidal power plant Dragon 12 in operation reaching key production performance milestone

GOTHENBURG, Sweden, June 12, 2025 /PRNewswire/ -- Minesto, leading ocean energy developer, today announces that its Dragon 12 tidal energy system (Luna), installed in Vestmannasund, Faroe Islands, has met a major production performance milestone: the longer tether enables a 25% increase of power ...

2025-06-12 17:59 1829

Project Update Vestmanna: Commercial Scale Powerplant: Dragon 12 grid connected, producing electricity

GOTHENBURG, Sweden, May 20, 2025 /PRNewswire/ -- Minesto, leading ocean energy developer, continues operation and testing activities in Vestmanna, Faroe Islands. The Dragon 12-megawatt tidal kite 'Luna' is in electricity production, following an upgrade period most prominently including a longer ...

2025-05-20 16:46 2000

Minesto joins World Expo 2025 in Osaka, Japan as part of the Swedish official delegation

GOTHENBURG, Sweden, May 14, 2025 /PRNewswire/ -- Minesto, leading technology developer in ocean energy, joins the World Expo 2025 in Osaka, Japan, as part of the Swedish official delegation and partner to the Nordic Pavilion. Today 14 May, Sweden celebrated its national day at World Expo, the del...

2025-05-14 17:01 2619

Minesto features in internationally broadcast documentary, 'Engineering Tomorrow'

GOTHENBURG, Sweden, April 30, 2025 /PRNewswire/ -- Leading ocean energy developer, Minesto, features in a new internationally broadcast documentary series `Engineering Tomorrow'. Minesto's pioneering underwater kite technology is showcased in the `Ocean Power' episode, selected as one of a few ti...

2025-04-30 22:33 2596

Invitation to Minesto's Webinar: Interim Management Statement Q1 2025

GOTHENBURG, Sweden, April 28, 2025 /PRNewswire/ -- On April 30, Minesto, leading ocean energy developer, will publish their Interim Management Statement 1 January - 31 March 2025. Dr Martin Edlund, CEO, and Gustav Kvibling, CFO, will present details of the report in a webinar and share key update...

2025-04-28 20:45 2092

Minesto's unique ocean energy technology at the centre of global branding campaign together with SKF

GOTHENBURG, Sweden, March 27, 2025 /PRNewswire/ -- Minesto, leading developer of ocean energy is selected by renowned bearing manufacturer SKF to be part of a large-scale international marketing brand campaign. The campaign "The Faroe Islands Space Program - a space program that never leaves eart...

2025-03-27 21:01 2019

Minesto selected to participate in GIA (Global Innovation Accelerator) programme by Swedish Energy Agency

GOTHENBURG, Sweden, March 7, 2025 /PRNewswire/ -- Minesto, leading ocean energy developer, has been selected to participate in GIA (Global Innovation Accelerator). The Global Innovations Accelerator Programme is initiated and funded by the Swedish Energy Agency, and run together with partner Busi...

2025-03-07 23:28 3844

Minesto publishes Year-End Report 2024

GOTHENBURG, Sweden, Feb. 27, 2025 /PRNewswire/ -- CEO Dr. Martin Edlund: "Minesto has now demonstrated competitive renewable energy production from an untapped natural resource based on a truly novel and proprietary innovation." Significant events October - December 2024 Minesto's work towards t...

2025-02-27 17:49 2402

Strong stakeholder engagement towards Minesto's first tidal energy Dragon farm in Hestfjord, Faroe Islands

GOTHENBURG, Sweden, Feb. 6, 2025 /PRNewswire/ -- On Monday 3rd February, ocean energy developer Minesto welcomed Faroese stakeholders, authorities as well as the public to a seminar at the Nordic House in Torshavn.Martin Edlund, CEO of Minesto, presented the company's vision for a sustainable ene...

2025-02-06 17:34 3075

Video: CEO presentation at Minesto's Capital Market Day 2024

The CEO presentation from Minesto's Capital Market Day is now available on the company's website and YouTube channel. The Capital Market Day was held on11 December 2024 at the company's workshop in Gothenburg, Sweden. GOTHENBURG, Sweden, Dec. 17, 2024 /PRNewswire/ -- A presentation was delivere...

2024-12-17 02:08 2609

Minesto completes Hestfjord Dragon Farm specification based on Dragon 12 achievements

GOTHENBURG, Sweden, Dec. 10, 2024 /PRNewswire/ -- After successful commissioning and four months of grid connected operation with Dragon 12, this autumn Minesto has focused on evaluation of powerplant performance, analysis of critical technical systems and operating procedures, as well as identif...

2024-12-10 19:08 2018

Invitation to Minesto capital market day

GOTHENBURG, Sweden, Nov. 15, 2024 /PRNewswire/ -- Minesto, leading ocean energy developer, welcomes investors, analysts and media to a capital market day on11 December 2024, 14.00-16.00 at Minesto's premises in Gothenburg, Sweden. Minesto CEO DrMartin Edlund will present the company's way forward...

2024-11-15 21:31 2407

Minesto presents at global climate change meeting COP29 in Baku, Azerbaijan

GOTHENBURG, Sweden, Nov. 15, 2024 /PRNewswire/ -- Minesto, leading ocean energy developer, is part of the official Swedish business delegation to United Nation climate change conferenceCOP29, taking place in Baku, Azerbaijan. On "Energy Day" on 15 November, Minesto will host a session on the role...

2024-11-15 00:39 2003

Minesto takes part in high-level energy transition conference and exhibition, Enlit Europe 2024, in Milan

GOTHENBURG, Sweden, Oct. 22, 2024 /PRNewswire/ -- Minesto is participating in one of the biggest international energy conferences, Enlit Europe 2024 taking place inMilan. The exhibition and conference, hosting 700+ international best-in-class technologies supporting energy transition, is held at ...

2024-10-22 14:13 2148

First-of-a-kind tidal dragon farm in the Faroe Islands moves forward

GOTHENBURG, Sweden, Oct. 14, 2024 /PRNewswire/ -- In the North Atlantic, leading ocean energy developer Minesto is moving forward with the pioneering build-out of a tidal energy site. The Hestfjord Dragon Farm is a first-of-a-kind tidal energy array with Minesto Dragon 12-kites with a total capa...

2024-10-14 15:49 1914

Minesto tidal energy kites featured on BBC News

GOTHENBURG, Sweden and VÄSTRA GÖTALAND, Sweden, June 24, 2024 /PRNewswire/ -- Swedish technology developer Minesto continues to attract global recognition for their unique tidal energy kites, generating electricity from tidal streams and ocean currents. The underwater kites and demonstration site...

2024-06-24 16:00 2239

Project update Vestmanna: Service and inspection of Dragon 12 - demonstration site attracting international study visits

Project Update Vestmanna: Four months of grid-connected operation with the utility-scale Dragon 12 is now followed by service and inspection. Ongoing operations continue to attract visits from international stakeholders and high-level decision-makers. GOTHENBURG, Sweden, June 12, 2024 /PRNewswir...

2024-06-12 22:41 2798

Minesto and Sev renew and update Power Purchase Agreement - underlining the value of tidal energy in the Faroese energy mix

GOTHENBURG, Sweden and VÄSTRA GÖTALAND, Sweden, June 10, 2024 /PRNewswire/ -- Leading ocean energy developer Minesto and pioneering Faroese utility company Sev have jointly renewed and updated the power purchase agreement (PPA). The price-level is adjusted to denote the total system value of tida...

2024-06-10 22:20 2768

Minesto presents performance data from Dragon Class starting at Annual General Meeting today

GOTHENBURG, Sweden, May 22, 2024 /PRNewswire/ -- In today's presentation at the AGM (Annual General Meeting), Minesto shares Dragon Class performance data based on accumulated analysis of Dragon 4 power production curve and verified simulation modelling. The data plays a key role in third-party t...

2024-05-22 16:46 2598

First three-month milestone of trouble-free Dragon 12 testing reached - generating valuable data on performance and robustness

GOTHENBURG, Sweden and VÄSTRA GÖTALAND, Sweden, May 8, 2024 /PRNewswire/ -- Minesto, leading ocean energy developer, today announces that for three months, since its initial installation inFebruary 2024, the tidal kite Dragon 12 has been successfully grid connected and delivers as expected at the...

2024-05-08 17:56 2293